Incineration Process Flowchart
No. process 1. Garbage receiving and treatment procedures, including: entrance loadometer, dumping platform, garbage bunker, garbage crane, ash bunker, ash crane, burning chamber, hearth system, etc. 2. Combustion air procedures, including: primary and secondary air blower, air preheater, air reheater, etc. 3. Bottom slag procedures, including: each bottom slag conveyor, ash ejector, vibration conveyor, etc. 4. Fly ash procedures, including: fly ash conveyor, pneumatic conveying system, fly ash storage tank, fly ash stabilizer, etc. 5. Waste metal procedures, including: magnetic selector, waste metal conveyor, waste metal bunker, waste metal compressor, waste metal crane, etc. 6. Steam procedures, including: high pressure steam distributor, steam turbine, power generator, steam condenser, etc. 7. Condensed water procedures, including: condensed water recycling equipment, such as condensed water tank, degassing & water feeding tank, etc. 8. Waste gas treatment procedures, including: dioxin preventiom equipment, nitrogen oxide removal equipment, semi-dry scrubber, bag filter dust collector, attraction exhaust fan, etc. 9. Wastewater procedures, including: inorganic wastewater treatment system, organic wastewater treatment system, sludge production system, etc.